Order of Inspections


1. Footing
2. Plumbing Rough
3. Return Air (If Applicable)

Inspections above must be completed before continuing on to #4.

4. Slab Inspection
5. Plumbing Top Out
6. Mechanical Rough Duct
7. Electrical Rough-In

Inspections above must be completed before continuing on to #8.

8. Electrical Underground Service (If Applicable)
9. Flat Work
10. Sewer And Service Lines (Water & Gas)
11. Electrical Final
12. Gas Final (If Applicable)
13. Plumbing Final
14. Mechanical Final
15. Building Final (Before The House/Building Is Occupied)