South Lubbock Storm Sewer Project

Cost: $42,500,000

(Past Project)


Schedule of Stages
April 2004 Design Complete
Package #1 Main Truck Line
July 2004 Project Bids
November 2004 Construction Begins
April 2008 Construction Complete